The Job Estimate allows you to create a high level, preliminary, calculation as well as the breakdown structures for the Job.
- The Estimate starts with defining the Job Deliverable.
- The next step is to decompose the deliverable in its main. Define the required elements in the Job Elements page.
- Select the Activities required for the Job in the Job Activities page
- For each Element the required Activities are selected to create the Element, with the New Job Acitivity action.
- For each combination of Job Element and Job Activity the estimated number of working days can be specified as well as the estimated cost of the activity.
- On the Job Element line the costs for Material, Equipment and Expenses can be added resulting in a total cost per Element and when all Elements are completed a total estimated cost for the Job is available.
- Use the Create Job Task Matrix action to create Job Tasks for each of the Element - Activity combinations.