ProjectBudget line actions

The following actions are available from the ProjectBudget ribbon:

Section Action Description
Process Copy Copy a budget line to another project task.
Move Move a budget line to another project task.
Split Split the quantity on a budget line to a new budget line.
Breakdown Break down a resource group into individual resources. Select resources from the resource group or from all resources. The quantity of the resource group is set to 0.
Copy to Planning Copy planning lines of the type Budget to planning lines of the type Planning.
Project Assembly BOM Create ProjectAssembly BOM Create a project version of an assembly BOM. You can add, modify, or delete components. The ProjectAssembly BOM is used when creating an assembly order. Otherwise, the default assembly BOM is used.
Show ProjectAssembly BOM Open the project assembly BOM to make modifications.
Delete ProjectAssembly BOM Delete the project assembly BOM.
Project Production BOM Create ProjectBOM and Routing version Create a project version of a production BOM and routing. More information.
Show ProjectBOM and Routing version Open the project production BOM and routing as selected or created on the ProjectBudget line. More information.
Cost Price per Lot Size Calculate the optimal lot size for a production item. More information.
Project Components Expand ProjectComponents BOM Copy the components of an assembly BOM to new budget lines based on the quantity of the assembly item. The quantity on the parent item is set to 0. You can still use the quantity field on the parent item to update the quantity of the components. Once expanded, you cannot create an assembly order for the parent item.
Collapse ProjectComponents BOM Collapse an expanded assembly BOM. After collapsing, you can create an assembly order again.
Add ProjectComponents Add a component to an expanded list. The component is then included in quantity updates of the parent item.
Other Apply Surcharge Model Calculate surcharges and add them as separate budget lines of the type surcharge. The calculation is based on the surcharge model set for the project task. See also: Surcharges.
Create Item Open the Create Item Wizard to create a new item and insert it as a project budget line. You can create the item by copying from another item, selecting an item template, or creating from a non-stock item.
Insert Ext. Texts Insert extended texts as set for the item, resource, or G/L account when these are not set as automatic extended text. The Business Central extended texts feature has been extended to include budget lines.

See also

Budgeting