How To: Copy Budget to Planning
In order to be able to track Budget vs Actuals IEM provides the "happy trail" of copying budget lines to planning lines and through create a connection between these lines. This connection is lateron visualized in the Forecasting function where an Estimate To Completion is calculated.
Copy Budget Lines from the Job Task
- From the Job Task open the Budget Lines either from the ribbon or from the Job Task Information fact box.
- In the Job Task Budget lines select the lines that need to be copied and click the "Copy to Planning" action
- Budget Lines of the type Resource No. as well as Group No. will be copied, for these lines the breakdown function is optional.
- Budget Lines of the type Item can only be copied when a No. is specified, when the Budget Line is for a Group, or Item Category, a "Group" line first needs to broken down in lines where the No. is specified.
- Based on the "Type" in the budget line either an Item Planning - or a Resource Planning line is created.
- Additional text lines (Extended Text) are linked to their parent line and copied as per that parent line.
- In the "Copy Job Budget to Planning" selection page the lines that can be copied are pre-selected, to NOT copy the pre-selected lines un-check the "Accept" field
Copy Budget Lines from the Job
- From the Job List click the ACTIONS tab and locate the Copy Budget to Planning action
- Click the Copy Budget to Planning action to open the Copy Job Budget to Planning selection page
- The Copy Job Budget to Planning selection page will list all Job Budget Lines which can be copied and have not been copied yet
- Click OK to copy the selected Budget Lines
The Copy Budget to Planning page provides the following actions
- The Select and Deselect actions in the ribbon toggles the Accept boolean for all selected lines in the page.
- The Split action in the ribbon allows you to split the quantity of the line:
- Select the line for which you want to split the quantity
- Click the Split action in the ribbon
- A Split Line message will pop up showing the Quantity Per of the selected line
- Type the Qty. to Split, = the quantity for the new line
- Click Yes to confirm
- The Show Copied Lines options shows all lines copied in previous actions, the copied lines are checked per line in the Copied field