Product Engineering - Engineering Change Management
How To : Setup Engineering Change Management
Choose the icon (Alt+Q) Type Engineering Change Management Setup
Field | Description |
---|---|
Enable ECR Services | Enables ECR and makes the ECR wizard appear in the various documents |
Allow edit on Order Line | When true User Entry Values lines are created which can be edited in the ECO |
Show current value | When true Existing Values lines are created and shown in the ECO (In blue) |
Create BOM Version | When true BOM Revisions will be created as new BOM Versions using the Revision Code as the Version No. |
Create Routing Version | When true Routing Revisions will be created as new Routing Versions using the Revision Code as the Version No. |
Item Template | Select a template to be used to complete new items |
Engineering Change Request Nos. | Select the number series to be used for the Engineering Change Requests |
Engineering Change Order Nos. | Select the number series to be used for the Engineering Change Orders |
Engineering Staging Nos. | Select the number series to be used for the Manual Engineering Change Orders |
ECR Priority | The priority of an ECR is initially calculated as Severity * Impact, the user can override this, suggested, priority at any time |
- Severity | The severity indicates the urgency of the requested change |
-- Low: | The product is fully functional but could be improved, usually in design. |
-- Medium: | The product is functioning but its use is inconvenient. |
-- High: | The product is still functioning but in a seriously constrained way. |
-- Critical: | Using the product is impossible and / or dangerous. |
- Impact | The impact indicates the, financial, consequences, of the requested change |
-- Low: | Current inventories and supply can be depleted first, phased out before the requested change is implemented. |
-- Medium: | Although the requested change is not interchangeable inventories and supply on the product are low. |
-- High: | The current, relatively high value, inventory has to be replaced and supply orders must be cancelled. |
User Defined Fields 01..10 | Set the captions for the User Defined fields in the EC Staging and Eng. Change Order |
The following items are included in the Product Engineering delivery package to assist you in the setup of Engineering Change Management
Engineering Change Management Lifecycles
Code | Description | File name |
---|---|---|
ECM-ECR | ECM Engineering Change Reques | N108 Lifecycle ECM-ECR.xml |
Import in Lifecycles | ||
ECM-ECR | Eng. Change Management Requests | ECM-ECR Workflow.xml* |